    5. Hals-Development has completed concreting the foundation slab of the Dubinin’Sky ..

    Business

    Hals-Development has completed concreting the foundation slab of the Dubinin’Sky business center

    Hals-Development Group has completed the construction of the foundation slab for the Dubinin’Sky business center. To lay the foundation structure, 13,431 cubic meters were needed. m of concrete mixture.

    Currently, the spacer system of the wall-in-soil pit enclosing structure is being dismantled at the construction site. Vertical waterproofing and monolithic walls are being installed.

    The next stage of construction will be the construction of the underground floors of the building – at the minus third level, reinforcement and concreting of vertical structures, as well as floor slabs, are now being carried out.

    “Construction of the Dubinin’Sky business center is progressing according to schedule. The installation of the tower crane for further work has been completed. We expect the project to reach zero by the end of April 2024. Commissioning of the entire facility is planned for the fourth quarter of 2025,” noted Deputy General Director – Head of the Development business area Ivan Zuev.

    Business Center Dubinin’Sky¹ – these are two 24-story towers on a single stylobate with class A offices on Dubininskaya Street. With a total area of ​​almost 106 thousand square meters. m more than 60 thousand sq. m. m will be occupied by office space with a capacity of up to 8,500 employees. Another 4 thousand sq. m. m is allocated for modern urban infrastructure in the form of a shopping gallery with restaurants, shops and other retail facilities in the stylobate. A fitness club with a swimming pool will open on the second floor.

    A comfortable barrier-free environment will be created throughout the complex. Landscaped public areas will appear: lawns, pedestrian sidewalks, summer verandas, parking for scooters and bicycles.

    In addition, the project provides for a three-level underground parking for 450 cars, including motorcycles and electric cars, as well as a surface parking lot for car sharing and taxis.

    ¹The areas are intended for rent

    Click to comment

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    Take A Look

    You may be interested in:

    Technology

    Hundreds of scientists have studied the genes of 9,500 plant species Researchers from all over the world have studied different types of flowers. They...

    News

    Greek police at the site where Dr Mosley's body was discovered. Photo: Jeff Gilbert The film crew on the boat were 330 yards offshore when...

    Politics

    The news about the tragic death of Alexandra Ryazantseva, an activist of the Euromaidan movement and a member of the Ukrainian armed forces, has...

    Auto

    The Chinese brand has completely declassified a new SUV for the home market. The model is offered with two “filling” options. The auto giant...