Most of the new equipment will be located in the machine assembly shop. According to the chief engineer of PJSC «TMZ» Vladimir Mikhailovich Schanikov, the machines are designed for machining parts of engines and automobile gear winches. A five-axis vertical milling machine is installed in the repair and tool shop. It will produce not only parts of the main production, but also tooling.
Commissioning is scheduled for the last week of August, and from September, the machines will be fully brought into the production process. By this time, it is necessary to train personnel to work on the new equipment, primarily operators of machine tools with program control.
In August, two core machines are expected to arrive at the iron foundry. New equipment at CLC is needed to produce a cast-iron cylinder head for a modernized tractor engine.
Six more machines for machining parts will arrive at the plant in autumn. They will be installed at the new production site in the housing of the units.
In the conditions of the country's technological development, today Russian enterprises pay great attention to the technical re-equipment of production sites. At "KAMAZ" Modernization of production has been and remains one of priority topics, investment in reengineering projects is growing.
One of examples — subsidiary of «KAMAZ» in the Yaroslavl region. Today, against the background of import substitution and growth in production volumes, the issue of technopark renewal is one of key issues for PJSC "TMZ". Along with new equipment, new jobs appear at the plant. In in connection with an increase in production volumes the plant is recruiting personnel in a number of working specialties. All divisions of «KAMAZ» now they are working in the direction of strengthening the technological independence of the country and satisfying the demand for automotive components and vehicles at the expense of domestic products.